News and Updates

Uncategorized / 20.10.2017

Dear Stakeholder: Below please find the project update for the week of October 13 and anticipated traffic control for the week of October 23, 2017. Paving Continues on East Prater Way [caption id="attachment_939" align="alignnone" width="600"] New roadway on Prater Way[/caption] [caption id="attachment_940" align="alignnone" width="600"] Old roadway removal on Prater...

Uncategorized / 13.10.2017

[caption id="attachment_935" align="alignright" width="600"] Beginning the week of October 23, Galletti Way at E. 4th Street will be closed.[/caption] Dear Stakeholder: Below please find the project update for the week of October 9 and anticipated traffic control for the week of October 13, 2017. Upcoming Rock Blvd. Marathon...

Uncategorized / 05.10.2017

[caption id="attachment_930" align="alignright" width="600"] Beginning the week of October 9, Prater Way will be reduced to one westbound only lane from Pyramid Way to Rock Blvd.[/caption] Dear Stakeholder: Below please find the project update for the week of October 2 and anticipated traffic control for the week...

News / 29.09.2017

[caption id="attachment_927" align="alignright" width="600"] Beginning the week of October 9, Prater Way will be reduced to one westbound only lane from Pyramid Way to Rock Blvd.[/caption] Dear Stakeholder: Below please find the project update for the week of September 25 and anticipated traffic control for the week...

News / 22.09.2017

[caption id="attachment_921" align="alignright" width="600"] Demolition of old curb, gutter and sidewalk on the north side of Prater Way east of Rock Blvd.[/caption] [caption id="attachment_922" align="alignright" width="600"] Storm drain improvements at Prater Way and 18th Street.[/caption] [caption id="attachment_920" align="alignright" width="600"] Paving operations on 10th Street at Prater Way.[/caption] Dear...

News / 15.09.2017

[caption id="attachment_918" align="alignright" width="600"] Bore pit where utilities will be relocated.[/caption] [caption id="attachment_917" align="alignright" width="600"] Crews will bore underneath the existing railroad track to relocate utilities.[/caption] Dear Stakeholder: Below please find the project update for the week of September 11 and anticipated traffic control for the week of...