News and Updates

News / 03.04.2018

Dear Stakeholder: Below please find the project update for the week of April 2 and anticipated traffic control for the week of April 9, 2018. [caption id="attachment_1030" align="alignright" width="600"] Construction crews pave 18th St. at Prater Way in Sparks.[/caption]   [caption id="attachment_1031" align="alignright" width="600"] Crews finish sidewalk at the...

News / 23.03.2018

Dear Stakeholder: Below please find the project update for the week of March 19 and anticipated traffic control for the week of March 26, 2018. [caption id="attachment_1026" align="alignright" width="600"] Construction crews work to place new light poles at 4th St. and Sage St. in Reno.[/caption] [caption id="attachment_1027" align="alignright"...

News / 09.03.2018

Dear Stakeholder: [caption id="attachment_1020" align="alignleft" width="300"] New storm drain improvements on 4th St. at the Wells Ave. underpass.[/caption] [caption id="attachment_1021" align="alignleft" width="300"] Crews work on constructing the foundation for the new bus rapid transit (BRT) station at Prater Way and El Rancho Dr.[/caption]               Below please find the project...

News / 02.03.2018

[caption id="attachment_1016" align="alignright" width="600"] Crews work on installing new traffic signal poles at Prater Way and Rock Blvd.[/caption] Dear Stakeholder: Below please find the project update for the week of February 26 and anticipated traffic control for the week of March 5, 2018. The project team has...

News / 23.02.2018

[caption id="attachment_1007" align="alignright" width="600"] RTC Creates Project Information Poster. RTC Public Information Officer Lauren Ball delivers a project informational flyer to a small business employee on 4th Street, highlighting how to learn more about the 4th Street/Prater Way Bus RAPID Transit Project.[/caption] Dear Stakeholder: Below please find...

News / 20.02.2018

[caption id="attachment_1001" align="alignright" width="600"] Sidewalk demolition on February 13, 2018.[/caption] [caption id="attachment_1002" align="alignright" width="600"] New concrete on February 14, 2018.[/caption] [caption id="attachment_1003" align="alignright" width="600"] New street lighting on February 16, 2018.[/caption] Dear Stakeholder: Below please find the project update for the week of February 12 and anticipated traffic control...

News / 10.02.2018

[caption id="attachment_996" align="alignright" width="600"] New sidewalks on 4th Street just east of 6th Street.[/caption] [caption id="attachment_997" align="alignright" width="600"] Utility improvements continue on 4th Street at Sutro Street.[/caption] Dear Stakeholder: Below please find the project update for the week of February 5 and anticipated traffic control for the week...

Uncategorized / 02.02.2018

[caption id="attachment_993" align="alignright" width="600"] Traffic will be moved to the south side of the roadway to accommodate removals on the north side.[/caption] Dear Stakeholder: Below please find the project update for the week of January 29 and anticipated traffic control for the week of February 5, 2018. Traffic...

Uncategorized / 26.01.2018

[caption id="attachment_989" align="alignright" width="600"] New Bus Rapid Transit Station at Prater Way and 15th Street[/caption] Dear Stakeholder: Below please find the project update for the week of January 22 and anticipated traffic control for the week of January 29, 2018. Construction Underway on New BRT Stations Construction is in...

Uncategorized / 19.01.2018

Dear Stakeholder: Below please find the project update for the week of January 15 and anticipated traffic control for the week of January 22, 2018. [caption id="attachment_980" align="alignright" width="600"] Paul and son Evan hope to create an establishment where patrons feel like family.[/caption] January 2018 Business Spotlight:  4th...