Project Weekly Update: July 5, 2018

Project Weekly Update: July 5, 2018

Dear Stakeholder:

Below please find the project update for the week of July 3 and anticipated traffic control for the week of July 9, 2018.

Reno Paving 

Phase 1 paving operations in Reno on 4th Street between Galletti Way and Montello Street are in process.  Galletti Way is OPEN. 6th Street at 4th Street is closed to through traffic from June 29 to July 18.  Please use signed detours. Traffic is reduced to one-way westbound until approximately July 28 on this section of 4th Street.

Phase 2 paving will begin around July 14 from Montello Street to Quincy Street. More details will be provided as the date approaches.

A process known as roadbed modification is used to remove, mix and replace the existing roadbed with a new, smooth roadway surface on 4th Street in Reno.

Traffic Control

  • East 4th is one-way westbound traffic only from Galletti Way to Montello St.
  • 6th Street at 4th Street is closed to through traffic from June 29 to July 18. Please use signed detours.
  • Traffic control on Prater Way/4th Street between Galletti Way and Evans Ave. includes lane reductions and side street closures. Businesses are open and accessible.
    For the safety of drivers, riders and crews, RTC bus routes 2, 5, 11, 13, 15, 25 and 26 are detoured. Access RTC Transit Services for more information. Detours will be in place throughout the project.

Notes
Weather permitting, traffic control may include sidewalk closures, lane closures and minor detours.
Possible lane shifts with flagger throughout the project corridor.
The RTC urges drivers, bicyclists and pedestrians to use extra caution in construction work zones.
Traffic control and work zones will be in place and changing frequently.  Use caution and look for flaggers for direction.  Brief delays can be expected.